Monday, December 24, 2012

Cubby House update

Being a while. Started the rendering, pictures say it all. Now Liz calls it a complex.








Saturday, December 1, 2012

Carrots gone bad

 
Carrots gone bad, aka going to seed.

Friday, July 6, 2012

Long day putting in the floor




I'm using n12 simply because it is cheaper than mesh.


I used timber blocks to support the square frame and keep it level. By the time I had to take them away to fill the floor, the concrete had harden up enough to safely remove them. I concreted in the sump pit a couple of days ago and covered the lid in plastic. It is important to have the lid there just so the concrete does not push in the sides making the lid not fit.


It started to rain yesterday, so I put up a canopy - just in case. The bent over rebar will be the ceiling.


The finished result, steel towel finish.

I used my ninja skills to jump out after finishing the toweling ;)

Wednesday, July 4, 2012

Retaining Wall for Fire Pit.


Retaining wall for the fire pit.

Monday, July 2, 2012

Washing, Foundations and Underpinning


Walls washed. The hole in the middle is for the sump.


Saturday, June 30, 2012

Concrete foundations


I need to underpin the walls. Placing the concrete tomorrow morning.

Saturday, June 23, 2012

Skipbin is full :)


Hole dug, bin is full. I even took out a bit for the firepit.

Excavation day 3


Hit 1.5m, the bottom, still a little bit left for tomorrow. 

I should mention that part of the cubbie area will have a concrete ceiling just below ground level. This will make the top of the cubbie smaller in area than the bottom. 

Friday, June 22, 2012

Excavation Day 2 , another 60cm














Louka is with me, it needs to go down another 30cm

I even put in a safety rail in case the kids that play in the park come by again.

Wednesday, June 20, 2012

Excavating

Took delivery of a 10m3 skip bin.

Started the excavation, day one - 60cm, 90cm to go.


Monday, June 18, 2012


Fourth and final wall. The next is the excavation.

Monday, May 21, 2012

diaphragm wall

It was pretty hard to take a picture of the excavation, so I took a video...

http://youtu.be/31Q05UoX1TE

Sunday, April 15, 2012

Cubby House

My next big project is a cubby house / firepit.

The cubby house is to be partially underground. and the fire put is to be sunken (around 450-500mm). The top of the cubby house will be around 0.9-1m and be a viewing platform/stage for Louka. The bottom bit will be the actual cubby house.



The first step is to remove the builder's toilet - done.



Second is to build what is called a diaphragm wall by the fence. I excavated a trench 100mm x 1400mm below the fence and filled it full of concrete and reo N12 @ 350mm . Being mostly sand, it was easy for the first metre. Then it was hard sandy clay. The idea behind a diaphragm wall is to enable "bulk excavation" without impacting the park. This wall is approximately half the final width of the wall.