The plumbing inspector came and queried the height between the main drain and downstairs bathroom floor waste. Fortunately it just made the minimun height. He finally signed off and that was good.
I finished the cages for the stand alone piers and for the sydney water piers down the north side of the house. Sydney water requires that their drain is protected by piering.
I've just got 6 piers in the middle of the house. Hopefully I will get these done tomorrow.