Saturday, August 22, 2009

Side Backfill

I finished off the north side back fill. I've only got the south side to go :). I think I will need to order another 10 cubic metres of gravel. I'm onto my second load now and I have almost finished moving it. It is not too bad considering I can carry about 0.1 cubic metres in a wheel barrow - only 100 trips. Interestingly that is about 3000 shovels.

I have worked out that I can confortably move a 14 ton / 10 cubic metres of gravel in 2 days - via wheelbarrow through the park.





The block layers did not come to finish off the job today. I'm a bit disappointed. He promised me that Doug will come on Tuesday.